You have 10 minutes for this test. You must provide us at the end of this time with an excel sheet, which will be printed. After you will have finished the test, we will discuss with you about your answers.
Part One:
A_C_T_E_D have foreseen the spending of 350,000 USD on different lines directly related to these activities. As part of its primary budget forecasting, the allocation of funds were as following:
_30% on pipeline extension,
_25% on distribution of water tanks,
_35% on distribution of waste metallic containers,
_10% on support staff and cost.
1) By using Excel, please precise the amount to be allocated to each of these lines.
After a call for tender, two contractors P1 and P2 were chosen on a 40%-60% basis for the activity “pipeline”. In accordance with A_C_T_E_D policies, it was decided to pay at the end of the week an advance which reaches 10% of the amount of the contract. Once 30% of work has been achieved at the end of the month, a further 25% would be paid.
2) Precise, for each contractor, the amount to be paid at the end of the week and the amount foreseen to be paid at the end of the month.
Part Two:
How would you enter the following transactions on a cash flow excel sheet:
3) What is the balance at the end of the month?